SHEET 1 OF 2 · SITE & SEQUENCE

KESTRA APARTMENTS — 14-MONTH CONSTRUCTION SEQUENCE

Building Envelope Remediation · Balcony Restoration, Cladding, Windows, Roofing & Paint · 4 Buildings / 280 Units

Sep 1, 2026 → Oct 31, 2027
14 months · 207,529 SF exterior
Occupied · 9:00–5:00 weekdays only
SPEED
Month 6
mid-February 2027
Schedule Position
of 14 months
Overall Complete
weighted by envelope SF, units & balconies
Buildings Active
peak 3 concurrent
Scaffold Sets Erected
 
Units Turned Over
of 280 units

Site Progress Map Drag the slider or press Play — footprints fill left→right as each building completes

Building Status

Concurrency Profile how many buildings are open at once

Work Phase Key colour = leading phase · code = Bid Form item

Scope Driving Duration Dueall takeoffs

Duration weighted 50% exterior SF, 30% unit count, 20% balcony count. Building 2 carries 28.3% of the total workload, Building 3 the least at 23.2%.

SHEET 2 OF 2 · CONTRACT SCHEDULE & BASIS

KESTRA APARTMENTS — 14-MONTH CONSTRUCTION SEQUENCE

Sep 1, 2026 → Oct 31, 2027 · 4 Buildings / 280 Units · Dueall Construction

Contract Schedule bar = phase duration · vertical line = selected month · ◆ = milestone

Sequencing Logic

  • Bldg 1 first. Mock-ups and SEG acceptance ride on the first building, so it carries the learning curve.
  • Bldg 4 second, in parallel. It sits across the pond with its own access, parking and laydown, so it does not compete with the courtyard cluster for logistics.
  • Bldg 2 third. Largest building (86 units, 86 balconies, 440 openings) gets the longest run, 7.0 months.
  • Bldg 3 last. It shares the pool courtyard with Bldg 1, so it starts only after Bldg 1 scaffold comes down and inherits released scaffold and a fully trained crew.

Constraints Driving the Plan

  • Buildings stay fully occupied. Work hours 9:00 AM to 5:00 PM weekdays only, no weekends or holidays without written Owner permission.
  • Weather barrier to completed cladding runs about 3.1 months per building, well inside the 9-month limit in Section 07250 Para 1.06.
  • Photo and video documentation of each building is delivered to Owner and SEG before that building starts.
  • ASTM E1105 water testing at 10% of reused openings per building, before scaffold release.
  • Peak manpower holds at 3 buildings active. 4 concurrent is never required.

Assumptions

  • Notice to Proceed September 1, 2026. Substantial completion October 31, 2027.
  • Base bid: window and door remove and reinstall (Items E, G). Alternates F and H would add roughly 3 weeks per building for lead time and staging.
  • Roofing carried as Alternate M, TPO single-ply membrane in lieu of the Item L.4 modified bitumen cap sheet. Tear-off, coping, tapered ISO (Items L.1 through L.3) and rooftop MEP incidentals (L.5) are unchanged. Duration is the same either way; tear-off and insulation drive the phase, not the membrane.
  • PT tendon anchor work (70 locations) runs as one roving crew, independent of building scaffold.
  • Durations weighted by exterior SF, unit count and balcony count per the Dueall takeoffs.
  • Sequence is subject to the Owner-approved building order confirmed at the pre-construction conference.