Dueall Construction

Inspection & Reporting Program

Kestra Apartments · Building Envelope Remediation

OwnerGreystar Worldwide, LLC
Engineer of RecordSlider Engineering Group, Inc.
Site10387 Vista Oaks Ct., Orlando, FL
Scope4 Buildings · 280 Units · 207,529 SF
ScheduleSep 1, 2026 → Oct 31, 2027
ConditionsFully occupied · 9:00–5:00 weekdays
01

How Dueall inspects and reports on this project

Kestra is a fully occupied envelope remediation. Almost everything that matters gets covered up within days of being built, and the resident is back on the balcony the week after. The inspection program exists so that the Owner and the Engineer of Record can see every assembly before it disappears, and so that a finding is a dated record with a photograph rather than a conversation on a scaffold.

What this document is

A representative sample, not the complete set. Seven inspection templates and eight reports are reproduced here to show the format, the level of detail, and how a finding travels from the wall to the Owner's inbox. The full Kestra program is larger. It adds trade-specific inspections for roofing, post-tension anchor repair, cement board siding, sealant work, mock-up acceptance, and third-party testing, along with any reporting the Owner or the Engineer of Record wants added.

The complete inspection and reporting matrix is built out during preconstruction with the Engineer of Record and issued for approval before mobilization. Nothing in this document should be read as the boundary of what gets inspected at Kestra.

7
templates sampled in this document

The same checklist every time

Seven of Dueall's standing templates, already in use on occupied restoration work and re-specified for the Kestra assemblies. The superintendent is not deciding what to look at. The checklist decides, and it does not get shorter when the schedule gets tight. The Kestra set is broader than what is shown here.

6
engineer hold points

Work stops at the gate

Six defined gates where the assembly does not advance until the Engineer of Record has looked at it. Weather barrier before lath. Flashing before cladding. Stucco final before paint. Each gate is requested in writing with a minimum of 48 hours notice.

100%
findings issued in writing

No verbal-only findings

A Fail response is entered against the specific line item with a comment and a photograph, and the record goes to the trade partner and to the Owner the same day. When it is corrected, the original Fail stays in the record next to the Pass that closed it.

5:00
pm daily log deadline

Reporting on a clock

The daily log is issued by 5:00 PM the same day, not the next morning. Manpower by trade and location, weather, field notes, photographs, and every inspection performed. Fourteen months of that is the project record.

7
Templates sampled here
35
Checklist sections shown
255
Checklist items shown
6
Engineer hold points
8
Reports sampled here
Procore
Where every record is created and kept
Platform

Every inspection and report shown here is created, answered, and closed in Procore

Answered at the wall

Inspections are opened and responded to in Procore on a phone at the assembly. Pass, Fail, or N/A, with the comment and the photograph attached to that line item before the inspector walks away. Nothing is transcribed from a notepad later.

Owner and Engineer have direct access

The Owner and the Engineer of Record are given Procore access on this project. Inspections, daily logs, photographs, RFIs, and submittals are visible as they are created. Nothing has to be requested, exported, or forwarded to be seen.

Reports are outputs, not re-entry

The daily log, the inspection records, and the deficiency register are generated from the same Procore data and distributed to the standing list. There is no second system to reconcile and no version of the record that only Dueall can see.

The closeout archive is already built

At completion the Procore record exports complete: every inspection, response, comment, photograph, and test report, organized by building and elevation, delivered with the closeout package per Section 01700.

02

The inspection set

Seven of the Kestra templates are shown: two safety templates that govern how the site runs, and five quality templates aimed at the assemblies that carry water. Select any card to open its full checklist in the library below. Additional trade templates are issued in the same format and live in the same Procore inspection library.

INSP-01Safety

Pre-Demolition Planning & Setup

When: Once per building, before any cladding, balcony, or roof demolition begins. Re-run at each new segment.
Owner: Dueall Site Superintendent
Reviewed by: QA/QC Manager, Engineer of Record
5 sections33 items
INSP-02Safety

Site Safety Compliance Review

When: Routine, on a schedule governed by the volume of activity on site. Typically every two weeks with all four buildings active.
Owner: Dueall Safety Manager
Reviewed by: Project Manager, Owner, Engineer of Record
3 sections67 items
INSP-03Quality

Lath & Stucco Accessories

When: Per elevation, per building, after weather barrier approval and before scratch coat. Ends in a hard hold point.
Owner: Dueall Field Engineer
Reviewed by: QA/QC Manager, Engineer of Record, Building Department
5 sections25 items
INSP-04Quality

Windows & Exterior Doors

When: Per opening group, per unit. Flashing is verified before the unit is set and again before cladding closes the opening.
Owner: Dueall Field Engineer
Reviewed by: QA/QC Manager, Engineer of Record
4 sections28 items
INSP-05Quality

Balcony Waterproof Deck Coating

When: Per balcony, after framing and decking replacement is accepted and before the balcony is released back to the resident.
Owner: Dueall Field Engineer
Reviewed by: QA/QC Manager, Engineer of Record
5 sections24 items
INSP-06Quality

Exterior Painting & Coatings

When: Per elevation, after the stucco final and building department inspection release the hold point.
Owner: Dueall Field Engineer
Reviewed by: QA/QC Manager, Owner
5 sections26 items
INSP-07Quality

Construction Workmanship Compliance Review

When: Rolling review across all active buildings. Every open assembly gets looked at whether or not a trade-specific inspection is due.
Owner: Dueall QA/QC Manager
Reviewed by: Project Manager, Owner, Engineer of Record
8 sections52 items
03

Checklist library

The full item list for each of the seven templates shown, as it will be issued at Kestra. Items marked HP are hold points where work stops until the Engineer of Record releases the assembly. Items marked DOC are documentation requirements that must be satisfied for the inspection to close. These seven are reproduced in full so the detail is visible. They are a sample of the Kestra library, not all of it. Each is configured as a Procore inspection template and answered line by line in the field.

INSP-01  ·  Pre-Demolition Planning & Setup

Kestra buildings stay occupied through demolition. This is the gate that proves the resident protection, scaffold, and utility isolation are in place before the first fastener comes out.

TypeSafety
TradeDemolition / Site Setup
ReferenceSection 01010, Section 01500, 29 CFR 1926 Subpart T
FrequencyOnce per building, before any cladding, balcony, or roof demolition begins. Re-run at each new segment.
Performed byDueall Site Superintendent
Distributed toQA/QC Manager, Engineer of Record
No.Inspection itemPassFailN/A
A. Planning & Setup
1.1Competent person assigned and documented for demolition operations at this building.
1.2Engineer survey reviewed; structural stability and hazard areas identified and marked.
1.3Pre-existing conditions photo and video documentation complete and issued to Owner and Engineer before start, per Section 01010 Para B.4.
1.4Pre-start meeting held with the cladding subcontractor covering demolition scope, sequence, and controls.
1.5Utility locations verified: gas, water, electrical, communications, low voltage.
1.6Utilities locked out and tagged out per LOTO procedures where isolation is required.
1.7Utility disconnection confirmed with written sign-off from the utility representative where required.
1.8Resident protection systems installed: covered walkways, overhead protection at entries, lit egress paths.
1.9Resident notification issued and posted; Life Safety Plan current and posted for the affected building.
B. Fall Protection, Barricades & Access Control
2.1Fall protection systems inspected and verified compliant: guardrails, anchors, harness and lanyard use.
2.2Scaffold inspected for access, stability, and tie-ins; signed and sealed engineered scaffold drawings on site.
2.3Barricades, cones, warning tape, and controlled access zone signage in place at grade below the work.
2.4Resident egress routes confirmed, clearly marked, and unobstructed at all hours.
2.5Controlled Access Zones established and documented.
2.6PPE availability, storage condition, and emergency access routes verified.
2.7Where balcony guardrails are removed, temporary guarding installed and unit balcony access controlled.
2.8Work confined to the 9:00 AM to 5:00 PM weekday window; site returned to residents at shift end.
C. Worker Training & PPE Verification
3.1PPE orientation confirmed for all Dueall and subcontractor personnel on the building.
3.2Field observation verifies proper PPE use: hard hat, eye protection, gloves, high-visibility.
3.3Respiratory protection used correctly where dust is generated.
3.4Dust control and water suppression equipment functional and staged before demolition starts.
3.5Subcontractor compliance spot checks conducted and documented.
3.6Removed material inspected to confirm adequate remaining substrate for weather barrier, lath, and future tie-in overlaps.
D. Active Demolition Supervision
4.1Removal sequence performed in the safest structural order for the conditions found.
4.2Fastener removal performed in a way that prevents flying debris toward occupied areas.
4.3Sheathing and framing inspected immediately as areas are exposed; damaged quantities recorded against the Unit Price line items and reported to the Engineer.
4.4Debris containment maintained: chutes where required, bins covered, labeled, and not overfilled.
4.5Dust suppression maintained continuously throughout operations.
4.6Work areas free of trip hazards, protruding fasteners, and unsafe debris piles.
E. Cleanup, Site Security & Exposure Protection
5.1End of shift cleanup verified: no loose debris, hazards, or unsecured tools left in resident areas.
5.2Waste bins and disposal zones closed, labeled, and secured.
5.3Open wall and deck areas dried in before shift end or protected against the forecast.
5.4Daily demolition documentation complete: log entry, photos, PPE records, and corrective actions issued to the responsible trade.
Every item records a response, the responder's role, and a time stamp. Any Fail requires a written comment and at least one photograph before the inspection can be closed.
04

Engineer hold points

A hold point is a gate, not a courtesy notice. The assembly behind it does not advance until the Engineer of Record releases it in writing. Each gate is requested a minimum of 48 hours ahead with the building, elevation, and readiness confirmation attached.

GateHold pointTriggeredWhat is verifiedReleased by
HP-1Pre-demolition releaseBefore any cladding, balcony, or roof demolition on a buildingResident protection, scaffold, utility isolation, and pre-existing conditions documentation verified.Dueall Superintendent, Engineer of Record
HP-2Weather barrier approvedBefore lath or siding on an elevationDrainable house wrap continuity, laps, seam tape, and opening integration verified while still visible.Engineer of Record
HP-3Opening flashing and anchorageBefore cladding closes a window or door openingSill pan, jamb and head flashing, anchorage per product approval, and ASTM E1105 results in hand.Engineer of Record
HP-4Lath and accessoriesBefore scratch coat on an elevationLath fastening, control joint cuts, weep screed height, and head flashing verified.Engineer of Record, Building Department
HP-5Stucco finalBefore paint preparation on an elevationThree-coat thickness, cure time, and building department inspection cleared.Engineer of Record, Building Department
HP-6Balcony deck watertightBefore traffic loading and before the balcony returns to the residentCoating thickness, terminations, penetrations, and drainage verified watertight.Engineer of Record

If a gate cannot be met on the requested date, Dueall reschedules the trade rather than proceeding. A covered assembly that was never inspected is opened back up at Dueall's cost.

05

Daily field log

Issued every work day by 5:00 PM to the Owner and the Engineer of Record. The log is the spine of the project record: it is what establishes who was on site, where they were, what the weather did, and which inspections were performed on any given day of the fourteen months.

Weather and observed conditions

Recorded high, low, and average temperature, precipitation since midnight and for the prior two days, humidity, wind, plus timed field observations at the start and middle of the shift with any weather delay flagged.

Manpower

Every company on site, headcount, hours, total hours, and the building and elevation they worked. This is what supports a delay claim, a weather day, or a manpower question twelve months later.

Field notes

Narrative by location with photographs attached. Progress, coordination items, conditions found on exposure, and anything the Owner or Engineer will want to know before the next walk.

Inspections performed

Every inspection run that day with start and end time, inspecting entity, type, location, and result. Third party and building department inspections are logged the same way.

Quantities on exposure

Sheathing, framing, and other unit price quantities recorded at the moment the condition is exposed and photographed, so they are agreed in the field rather than reconciled from memory at the pay application.

Distribution through Procore

The log is published in Procore and distributed automatically to the Owner and the Engineer of Record. Trade partners receive the portions that concern their scope. Nothing waits for a weekly meeting to be visible.

Illustrative sampleThe tables below show the format of a Kestra daily log using representative activity. They are examples of structure, not a record of work performed.
Manpower — illustrative day
CompanyLocationActivityWorkersHours
Cladding SubcontractorBuilding 1 › NorthScaffold erection756.0
Cladding SubcontractorBuilding 1 › EastThree-coat stucco, scratch coat1080.0
Cladding SubcontractorBuilding 4 › SouthWeather barrier and seam tape756.0
Painting SubcontractorBuilding 1 › WestExterior primer216.0
Painting SubcontractorBuilding 1 › WestExterior finish coat864.0
Dueall ConstructionBuilding 4 › SouthCarpentry and sheathing repairs864.0
Dueall ConstructionSite wideProject management and supervision864.0
Window SubcontractorBuilding 4 › NorthArched window removal and reinstall540.0
Window SubcontractorBuilding 1 › NorthOverhead and condenser protection216.0
Window SubcontractorBuilding 2 › EastCovered porch door installation324.0
Roofing SubcontractorBuilding 1 › WestCoping and edge metal216.0
Roofing SubcontractorBuilding 4 › SouthRoof tear-off and dry-in864.0
Balcony SubcontractorBuilding 1 › EastDeck coating base coat432.0
Total on site74592.0
Field notes — illustrative day
LocationNote
Building 1 › NorthScaffold erection continues and is scheduled to top out today. Pre-demolition walk with the Engineer of Record is set for tomorrow morning.
Building 1 › EastScratch coat completed Saturday. Crew hydrating stucco and correcting the areas flagged on Friday's workmanship review. Scratch coat inspection requested for 12:30 today.
Building 1 › WestPainting subcontractor continuing primer and finish coat on the west elevation. Control joints masked and verified before spray.
Building 4 › SouthSheathing replacement at the south elevation running above the estimated percentage. Quantities photographed and logged to the Unit Price line for Engineer verification.
Building 2 › EastCovered porch doors set. Threshold pans verified before units were installed.

Company names in the sample are shown by role. On the live project the log carries the actual trade partner names, and the Owner and Engineer receive the unredacted version.

06

What a completed inspection record looks like

A closed inspection is not a tick sheet. It carries the response history for every item, the comment that explains a Fail, the correction, and the re-inspection that closed it. This is the format the Owner and the Engineer of Record receive.

Illustrative sampleRepresentative record showing how findings and their close-out appear. Locations and results are examples, not Kestra field data. This is a Procore inspection record. The Owner and the Engineer of Record can open the live version and every attached photograph directly.
24/24
Items Inspected
21
Conforming
2
Deficient
1
N/A
0
Neutral

INSP-04  ·  Windows & Exterior Doors #12

TypeQuality
TradeWindows / Openings
LocationBuilding 1 › North Elevation › Units 104–108
Inspection DateIllustrative
StatusClosed
Created ByDueall Field Engineer
ResponsibleWindow Subcontractor
AssigneeDueall Field Engineer
DescriptionFive openings, sill pan and jamb flashing verified before units set
No.Inspection itemResponseActivity and comments
A 1.6Rough openings square, plumb, and level; diagonals within 1/8 inch.PassField Engineer responded Pass. Four of five within tolerance on first check.
B 2.2Self-adhering membrane sill pan installed, turned up jambs, corners formed.PassField Engineer responded Pass after re-work. See B 2.5.
B 2.5Membrane fully rolled. No fishmouths, wrinkles, or unbonded edges.FailField Engineer responded Fail. Comment: fishmouth at both lower corners, unit 106. Membrane relieved, re-cut, primed, and re-rolled by the window subcontractor same shift. Re-inspected and closed Pass.
C 3.4Sill flange left with a drainage gap at each corner.FailField Engineer responded Fail. Comment: sill flange continuously sealed at units 105 and 106. Sealant cut back 2 inches at each corner and weep path verified with water. Re-inspected and closed Pass.
C 3.5Anchors and fasteners installed per the product approval schedule.PassField Engineer responded Pass. Fastener count and edge distance verified against the approval schedule at each opening.
D 4.1ASTM E1105 water infiltration testing at the required sample rate.PassIndependent testing agency. One opening tested in this group. No infiltration at 6.0 psf. Report issued to the Engineer.
D 4.5HOLD POINT: approved by the Engineer before cladding closes the opening.PassEngineer of Record released the hold point on the re-inspection walk. Lath released for this elevation.
D 4.6PHOTO: exterior wide, sealant, flange, and anchorage close-ups.Pass18 photographs attached to the record and pushed to the Owner and Engineer with the daily report.
Attached photo set (excerpt)
Opening flashing complete before stucco
Opening flashing complete before stucco
Arched openings, units set and sealed
Arched openings, units set and sealed
Opening protection during adjacent work
Opening protection during adjacent work
Completed elevation at the entry
Completed elevation at the entry
Eight of twenty-four items shown. The two deficiencies remain permanently in the record alongside the responses that closed them. Photographs stay attached to the line item they support and travel with the record in Procore.
07

How a deficiency moves

Five steps, and none of them are optional. The point of the sequence is that a finding cannot quietly disappear: it is written down before it is fixed, and the record of the fix is attached to the original item.

1

Observed

The finding is entered against the specific checklist item with a Fail response, a written comment, and a photograph. Nothing is recorded verbally.

Field Engineer / Superintendent
2

Issued

The record is pushed the same day to the responsible trade partner and copied to the Owner and the Engineer of Record.

QA/QC Manager
3

Corrected

The trade partner corrects the work and notifies Dueall. If the item sits behind a hold point, that assembly does not advance.

Responsible trade partner
4

Re-inspected

The original item is re-responded, not overwritten. The Fail stays in the permanent record alongside the Pass that closed it.

Field Engineer
5

Closed or escalated

Closed with photo evidence. A repeat finding is escalated in writing to the trade partner's management and carried on the weekly register until the pattern stops.

QA/QC Manager

Repeat findings are the real signal. A single missed weep is a correction. The same missed weep on three elevations is a training or staffing problem at the trade partner, and it gets raised as one in writing.

08

Reporting and distribution

Eight standing deliverables, all generated from Procore rather than assembled by hand. The Owner and the Engineer of Record are on every one of them by default, and nothing on this list requires a request. This is the core reporting set shown as a sample. Additional project-specific reports are added during preconstruction at the Owner's or the Engineer's direction, and any Procore report can be scheduled to a distribution list.

DeliverableContentsFrequencyIssued toTiming
Daily field logWeather and observed conditions, manpower by trade and location, field notes with photographs, inspections performed that day.Every work dayOwner, Engineer of RecordBy 5:00 PM the same day
Quality inspection recordThe full checklist with every response, every comment, hold point status, and the attached photo set.Per inspectionOwner, Engineer, responsible trade partnerSame day as the walk
Hold point noticeWritten request for inspection at a defined gate, with the assembly, location, and readiness confirmation.Per gateEngineer of Record, OwnerMinimum 48 hours before the gate
Deficiency registerEvery open finding with responsible party, due date, and the evidence that closed it.WeeklyOwner, Engineer, trade partnersMonday, with the weekly report
Site safety compliance reviewOSHA compliance, occupied-site resident protection, and stormwater sections with corrective actions.Every two weeksOwner, Engineer, all trade partnersWithin 24 hours of the walk
Weekly progress reportSchedule status by building, quantities logged to unit price lines, RFI and submittal status, photo set.WeeklyOwner, Engineer of RecordMonday, before the weekly meeting
Pre-existing conditions packagePhoto and video record of the building and adjacent site features before any work starts.Per buildingOwner, Engineer of RecordBefore mobilization on that building
Closeout packageOperations and maintenance manuals, warranties, as-built documentation, and the full inspection and photo archive.At completionOwner, Engineer of RecordPer Section 01700
09

Photo and records standards

On an envelope project the photograph is the evidence. Five rules govern how the record is built so that it is usable at closeout and defensible years later.

Field photographsThe images below are pulled from Dueall inspection records and daily logs on comparable occupied exterior restoration work. They are shown to illustrate the documentation standard and the type of condition that gets captured. They are not photographs of the Kestra site.

Overall plus detail

Every inspection carries a wide shot that establishes location and close-ups of the specific condition being judged.

Before cover, always

Any concealed condition is photographed before it is covered. Weather barrier, flashing, lath, and framing are documented while visible.

Tied to the item number

Photographs are attached to the checklist item they support, not dumped into a folder. The item number is the index.

Pre-existing conditions

A full photo and video record of each building and the adjacent site is delivered to the Owner and Engineer before mobilization on that building.

Organized archive

The archive is kept by building, elevation, and date through the project and delivered complete at closeout.

Pre-demolition
Pre-demolition

Balcony with the guardrail removed and scaffold access overhead. The condition is recorded at the pre-demolition walk, before any removal starts.

Site safety
Site safety

Scaffold planking and toe board from below. Full planking, midrail, and toe board are checked at every level in use.

Site safety
Site safety

Scaffold platform at balcony level. Guarding and access are verified before any trade works off the deck.

Stormwater
Stormwater

Inlet protection at a drainage structure. Stormwater controls are photographed at each routine review.

Lath and stucco
Lath and stucco

Weather barrier and lath complete at a building corner. Elevation overview taken before the scratch coat hold point.

Lath and stucco
Lath and stucco

Opening jamb: lath tied and accessory set. Concealed work is always photographed before it is covered.

Lath and stucco
Lath and stucco

Base of wall at the weep screed. Height above grade and an open drainage kerf are verified and recorded.

Stucco
Stucco

Scratch coat placed and being moist cured. Cure condition is part of the record, not just the finished surface.

Stucco
Stucco

Scratch coat hydration in progress. The daily log carries the activity, the location, and the photograph together.

Stucco
Stucco

Scratch coat complete across a full elevation. Wide shot that establishes location for the close-ups filed with it.

Finish and paint
Finish and paint

Finish coat, decorative band, and texture at an entry. Judged against the approved mock-up, not against a description.

Finish and paint
Finish and paint

Completed entry at a released area. The final elevation photograph is what closes the record for that location.

10

What we need, and what you get back

What Dueall needs from the Owner and Engineer

  • A named alternate reviewer at each hold point. Six gates across four buildings for fourteen months. A single reviewer on vacation should never stall an elevation.
  • Timely mock-up acceptance. The approved mock-up is the standard every downstream inspection judges against. A delayed acceptance walk does not stall one elevation, it stalls the standard.
  • A standing distribution list on day one. Confirm who receives the daily log, the inspection records, and the weekly register so nothing is routed by guesswork.
  • Agreement that unit price quantities are verified at exposure. Sheathing and framing percentages get counted and photographed when the wall is open, signed in the field, not reconciled later.
  • Confirmation the deficiency register format is acceptable as the single source of truth for open items, so we are not maintaining two lists.

What the Owner and Engineer get back

  • A dated, photographed record of every assembly before it was covered. Weather barrier, flashing, lath, and framing, by building and elevation.
  • Findings while they are still cheap. A fishmouth caught at the sill costs an hour. The same detail found after stucco and paint costs an elevation.
  • Quantities agreed in the field. Unit price work is settled at the moment of exposure, which keeps it out of the pay application dispute.
  • One organized archive at closeout. Inspections, photographs, test reports, warranties, and as-builts, delivered by building and elevation per Section 01700.
  • Trade partners who know they are being measured against the same checklist every time, with repeat findings escalated in writing.